RCC, Saylorville Lake, IA

View Photos

Working night and day for 72 hours straight with the Army Corps of Engineers, Central Iowa Ready Mix poured 1300 yards of concrete and 3500 yards of roller compacted concrete before the water was projected to break the reservoir’s emergency spillway. Central Iowa Ready Mix finished in the nick of time as water began coming over the re-enforced spillway July 1st and did not stop until July 7th, 2010.

Project Statistics

Yards: 4,800
Trucks: 480 Loads
Temperature: High Summer Heat
Time of Year: Summer